Stege Sanitary District Pipeline Replacement and Rehabilitation Project Begins March 2019

Stege

Each year Stege Sanitary District schedules a pipeline replacement and rehabilitation project throughout its sanitary sewer collection system. An encroachment permit will be issued for this work which will begin early March, weather permitting. Projects are selected based on pipeline condition information obtained from video inspections, field maintenance reports, economic analysis and on the financial resources of the District. This year Stege has contracted with D’arcy and Harty Construction Inc. to replace the sewer mains on the following streets:

  • Tulare Ave between Barrett Ave. and Charles Ave. - Anticipated work to take place from 3/6-3/8  
  • Yuba St. between Barrett Ave. and Zara Ave. - Anticipated Work to take place from 3/8-3/11
  • Tuller Ave between Barrett Ave. and Silva Ave. - Anticipated Work to take place from 3/12-3/18
  • Yuba St. between Barrett Ave. and Hillside Ave. - Anticipated Work to take place from 3/25-3/28
  • Sewer main easement between Alta Punta Ave. and Ludwig Ave. and from MacDonald Ave. to Jordan Ave. - Work dates are to be determined

Engineering staff will be issuing an Encroachment Permit for this work, which is anticipated to begin early March and be completed in late May 2019, weather permitting. The work hours will be from 8:00 A.M. to 5:00 P.M., Monday to Friday. During this process, heavy equipment will be parked at on-street locations and some streets will be closed to through traffic, so access to driveways and parking will be temporarily affected by the construction. Stege’s contractor will post notices on barricades 72 hours prior to any parking restrictions and hang notices on doors prior to the start of construction. For more information about the sewer replacement and rehabilitation project, please contact Stege’s project manager, Paul Soo, via email or (510) 524-4668. For more information on the City’s Encroachment Permit, please contact Ana Bernardes, the City’s Engineering Manager via email or (510) 215-4385.